The building housing the City Hall & Police Station is 70 years old and was originally constructed to store building materials. It was never meant to house the business functions associated with a City Hall and was definitely not intended to accommodate a police department and emergency management functions. The conditions of our current City Hall & Police Station building are well below what would be expected from a facility housing public safety, emergency management or other critical municipal operations. Please use this page as a reference to all activities related to the project as we plan for it's future replacement.
Looking For The Latest Design & Budget Documents? Expand Materials Provided Below
- 11/28/2023 - City will be providing a forum for public input on the City & Police Station Projects
- 11/06/2023 - CIDA will be presenting Council with an updated Schematic Design & updated City Hall costs
- 10/17/2023 - CIDA will be presenting Council with an updated Schematic Design based off of Community Outreach Event #5
- 10/05/2023 - City will be holding Community Outreach Event #5 to gather public input for building layouts
- 09/18/2023 - CIDA will be presenting Council building layout updates
- 08/23/2023 - City will be holding Community Outreach Event #4 to gather public input for building layouts
- 06/13/2023 - City selects building locations and continues funding discussion of City Hall / Police Station project
- 05/30/2023 - City will continue funding discussion and next steps of City Hall / Police Station project
- 05/16/2023 - City will be holding Community Outreach Event #3 to gather public input for site location
- 04/05/2023 - City will continue funding discussion and next steps of City Hall / Police Station project
- 03/28/2023 - City will be having a discussion about funding the City Hall / Police Station project
- 03/14/2023 - CIDA will be presenting Council with a building program review and costs
- 01/11/2023 - CIDA will be presenting Council with a report about input received from the community outreach events
- 11/12/2022 - City will be holding Community Outreach Event #2 to gather public input for site planning
- 11/01/2022 - City hires Emerick Construction for City Hall/Police Department CM/GC services
- 10/25/2022 - City will be holding Community Outreach Event #1 to gather public input for site planning
- 09/13/2022 - City hires CIDA, Inc. to design new City Hall/Police Department
- 08/12/2022 - City issues RFP for City Hall/Police Department Construction Manager/General Contractor Services (CM/GC)
- 06/17/2022 - City issues RFP for City Hall/Police Department Design & Construction Documents
- 09/28/2021 - City Council selects E. Gower Street site for new City Hall
- 03/10/2020 - City Hall Vetting Committee will provide report to Council
- 12/10/2019 - City Hall Vetting Committee will be providing recommendations to Council
- 10/10/2019 - SRG will be providing Council with an updated City Hall Facilities Report including additional sites
- 10/01/2019 - City Council establishes City Hall/Police Station Project Vetting Committee to validate Facilities Report
- 12/18/2018 - SRG will be providing Council with the City Hall Facilities Report
- 10/10/2018 - City hires SRG Partnership for City Hall Facilities Report & Program
- 08/10/2018 - City issues RFP for City Hall Facilities Report
- 04/10/2018 - City reviews City Hall Building System Analysis with Council
- 03/06/2018 - City hires Tolovana Architects to study City Hall Code/Safety/Structure
Current Design & Budget Documents
- City Hall & Police Station Current Design Documents - Most recent CIDA Design
- City Hall & Police Station Current Budget Documents - Most recent Emerick Budget Estimates with options
Schematic Design Phase:
- City Hall & Police Station Schematic Design Update #3 with Updated Costs - 11/06/2023 by CIDA
- City Hall & Police Station Schematic Design Update #2 with Police Station Costs - 10/17/2023 by CIDA
- Police Station Cache Site Geotech Report - 10/9/2023 by Geotech Solutions
- City Hall & Police Station Schematic Design Update #1 - 10/5/2023 Community Outreach Event #5 with CIDA
- City Hall Schematic Design - 8/23/2023 Community Outreach Event #4 with CIDA
- Police Station Schematic Design - 8/23/2023 Community Outreach Event #4 with CIDA
- City Hall Gower St. Geotech Update - 7/31/2023 by Geotech Solutions
Pre Design Phase:
- City Hall / Police Station Preliminary Cache Site Geotech Update - 5/26/2023 by Geotechnical Resources, Inc. (GRI)
- City Hall / Police Station Program Review & Costs - 3/14/2023 Review with CIDA
- City Hall / Police Station Programming Discovery Packet - 1/11/2023 CIDA Report from Community Outreach Events
- City Hall / Police Station 2019 Facilities Report, Volume 1 (Summary) - 10/10/2019 by SRG Partnership, Inc.
- City Hall / Police Station 2019 Facilities Report, Volume 2 (Room Data & Diagrams) - 10/10/2019 by SRG Partnership, Inc.
- City Hall / Police Station 2019 Facilities Report, Volume 3 (Appendix) - 10/10/2019 by SRG Partnership, Inc.
- South Wind 2018 Geotechnical Feasibility Report - 3/14/2019 by Geotechnical Resources, Inc. (GRI)
- City Hall / Police Station 2019 Site Selection Analyses - 1/9/2019 by CB Community Development
- City Hall 2018 Building System Analysis - 4/3/2018 by Tolovana Architects
- Gower Street 2011 Geologic Hazard Report - 5/4/2011 by Chinook GeoServices, Inc.
Previous Reports & Discussion:
- South Wind 2014 Master Plan - by CB Master Plan Advisory Committee
- South Wind 2013 Geotech Report - by Horning Geosciences
- South Wind 2013 Geotech Report Addendum - by Horning Geosciences
- South Wind 2013 Environmental Site Assessment - by Assessment Associates, Inc.
- City Hall / Police Station Problem & Goal Statement - by CB City Manager
- City Hall / Police Station Problem & Goal Statement - by CB Mayor
- City Hall / Police Station Emergency Management White Paper - by CB City Manager
City Staff:
Bruce St. Denis
City Manager
Phone: (503) 436-8050
Email: stdenis [at] ci.cannon-beach.or.us
Rusty Barrett
IT Director
Architect:
Leslie Jones, LEED AP BD+C
Associate Architect
CIDA, Inc.
Construction Manager / General Contractor:
Jordan Fell
Executive Vice President
Emerick Construction
Will Somme
Project Manager
Emerick Construction
Project Website:
ci.cannon-beach.or.us/city-hall
Email:
- cityhall [at] ci.cannon-beach.or.us (City Hall), City of Cannon Beach
- Project Architect, CIDA Inc.